Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
39W803 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 3583(1)/।।।(2)/21-08(एम.एल.ए.)/2017 टी.सी.-। दिनांक 10.09.2021
TS Amount (lakhs) : 156.12 Lacs
Financial Detail
Sanction Cost : 156.12 Lacs
Resanction Cost : 156.12 Lacs
Exp. Upto Last Fy : 155.46 Lacs
For CFY 2024-2025
Remaining : 0.66 Lacs
Demand : 0.66 Lacs
Allotment : 0.66 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 155.46 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 8 months ago
10 Sep 2021
Tentative Completion date:
1 year 1 month ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3.00 किमी0 में पी.सी. द्वारा डामीरकरण कार्य पूर्ण।
पीसीआर गठित ।
-- as on 21-Nov-2023
Physical Peramenters