Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.1 | 1.1 | 0.000 | 1.1 | 0.000 | 0.000 |
39W804 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 4779(1)/।।।(2)/21-08(एम.एल.ए.)/2017 टी.सी.-।।। दिनांक 05.10.2021
TS Amount (lakhs) : 38.96 Lacs
Financial Detail
Sanction Cost : 38.96 Lacs
Resanction Cost : 38.96 Lacs
Exp. Upto Last Fy : 10.95 Lacs
For CFY 2024-2025
Remaining : 28.01 Lacs
Demand : 28.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 10.95 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
2 years 7 months ago
05 Oct 2021
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
0.30 किमी0 में पहाड कटान कार्य पूर्ण। शेष पहाड कटान का कार्य प्रगति पर है। -- as on 21-Nov-2023
Physical Peramenters