Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
39W833 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. ।/59301/2022 ई-फाइल सं09-33399 लोक निर्माण अनुभाग-2 दिनांक 30.08.2022
TS Amount (lakhs) : 165.22 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
165.22
Resanction Cost :
165.22
Tentative Cost :
165.22
Exp. Upto Last Fy : 142.91
For CFY 2024-2025
Remaining : 22.31
Demand : 22.31
Allotment : 22.31
Exp in CFY : 2.42
Total Up to Date Exp : 145.33
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 10 months ago
30 Aug 2022
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
5.00 किमी0 में पहाड कटान कार्य पूर्ण। -- as on 30-Apr-2024
Physical Peramenters