Work Profile Report [39W833]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा.सं. ।/59301/2022 ई-फाइल सं09-33399 लोक निर्माण अनुभाग-2 दिनांक 30.08.2022
TS Amount (lakhs) : 165.22 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
165.22
Resanction Cost :
165.22
Tentative Cost :
165.22
Exp. Upto Last Fy :
142.91
For CFY 2024-2025
Remaining :
22.31
Demand :
22.31
Allotment :
22.31
Exp in CFY :
21.93
Total Up to Date Exp :
164.84
In Maintenance After Completion
Sanction on : 2 years 3 months ago
30 Aug 2022
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 8 months 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
5.00 किमी0 में पहाड कटान कार्य पूर्ण। -- as on 30-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: