Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 4.600 | 0.000 |
39W930 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. ।/111987/2023 ई-फाईल सं0 50408 /लोक निर्माण अनुभाग-2 दिनांक 31.03.2023
TS Amount (lakhs) : 322.34 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
322.34
Resanction Cost :
322.34
Tentative Cost :
322.34
Exp. Upto Last Fy : 117.08
For CFY 2024-2025
Remaining : 205.26
Demand : 205.26
Allotment : 72.94
Exp in CFY : 0.00
Total Up to Date Exp : 117.08
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 40 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
1 month 2 weeks from now
03 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
4.60 किमी0 में सोलिंग कोट व इण्टर कोट का कार्य पूर्ण। शेष शेष इण्टर कोट, दीवार व स्कपर निर्माण कार्य प्रगति में। -- as on 14-Jul-2024
Physical Peramenters