Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 0.000 |
39W930 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. ।/111987/2023 ई-फाईल सं0 50408 /लोक निर्माण अनुभाग-2 दिनांक 31.03.2023
TS Amount (lakhs) : 322.34 Lacs
Financial Detail
Sanction Cost : 322.34 Lacs
Resanction Cost : 322.34 Lacs
Exp. Upto Last Fy : 117.08 Lacs
For CFY 2024-2025
Remaining : 205.26 Lacs
Demand : 205.26 Lacs
Allotment : 26.54 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 117.08 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 25 %
Sanction on :
1 year 1 month ago
31 Mar 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
4.50 किमी0 में सोलिंग कोट व 1.00 किमी0 में इण्टर कोट का कार्य पूर्ण। -- as on 31-Mar-2024
Physical Peramenters