Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9 | 9 | 0.000 | 9 | 9.000 | 6.800 |
39W998 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष लो0नि0वि0 उत्तराखण्ड, देहरादून का पत्र संख्या 895/07याता-पीएमजीएसवाई -नि0-।।। दिनांक 16.05.2023
TS Amount (lakhs) : 305.41 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
305.41
Resanction Cost :
305.41
Tentative Cost :
305.41
Exp. Upto Last Fy : 122.71
For CFY 2024-2025
Remaining : 182.70
Demand : 182.70
Allotment : 60.00
Exp in CFY : 45.55
Total Up to Date Exp : 168.26
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 80 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
6.80 किमी0 में पीसी का कार्य पूर्ण। शेष भाग में सीसी का कार्य प्रगति मंे। -- as on 25-Jun-2024
Physical Peramenters