Work Profile Report [3W261]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1648(।)/।।।(2)/13-52(प्रा.आ.)/2012 दि. 04.03.2013
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
35.28
Resanction Cost :
35.28
Tentative Cost :
10.46
Saving
24.82
Exp. Upto Last Fy :
0.46
For CFY 2025-2026
Remaining :
34.82
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.46
Alignment Approved
Sanction on : 12 years 10 months ago
04 Mar 2013
Physical Progress:
At start of FY 2025-2026 :
90 %
Up to Date :
90 %
Tentative Completion date on : 1 year 2 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
नापभूमि प्रतिकर प्रस्ताव गठन की कार्यवाही गतिमान। -- as on 02-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: