Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 0.000 | 0.000 |
3W322 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1527/।।। (2)/15-01(मु.म.घो.)/2015 दि0 28.02.2015
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 44.10 Lacs
Resanction Cost : 44.10 Lacs
Exp. Upto Last Fy : 7.24 Lacs
For CFY 2024-2025
Remaining : 36.86 Lacs
Demand : 15.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 7.24 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
9 years 2 months ago
28 Feb 2015
Tentative Completion date:
1 year 10 months from now
31 Mar 2026
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
द्वितीय चरण की स्वीकृति प्राप्त। स्वीकृति में सेतु निर्माण संभव न हो पाने के कारण पुनरीक्षित आगणन रू0 1482.00 लाख का गठित कर क्षेत्रीय कार्यालय अल्मोड़ा द्वारा दि0 05.07.2023 को शासन को प्रेषित, स्वीकृति अपेक्षित। -- as on 11-Sep-2023
Physical Peramenters