Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
3W326 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1835/।।। (2)/15-03(मु.म.घो.)/2015 दि0 19.03.2015
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 27.64 Lacs
Resanction Cost : 27.64 Lacs
Exp. Upto Last Fy : 0.27 Lacs
For CFY 2024-2025
Remaining : 27.37 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.27 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
9 years 2 months ago
19 Mar 2015
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
मुआवाजा प्रस्ताव गठित। सत्यापन किया जा रहा है। -- as on 08-Apr-2024
Physical Peramenters