Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.5 | 7.5 | 7.5 | 0 |
3W479 :
Administrative Approval Detail : शा0स0 1260/।।।(2)/19-50(एम0एल0ए0)/2018 दिनांक 06.02.2019
TS Amount (lakhs) : 383.89 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
383.89
Resanction Cost :
383.89
Tentative Cost :
383.89
Exp. Upto Last Fy : 363.69
For CFY 2024-2025
Remaining : 20.20
Demand : 4.00
Allotment : 4.00
Exp in CFY : 0.00
Total Up to Date Exp : 363.69
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 5 months ago
06 Feb 2019
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
2 years 8 months ago
30 Oct 2021
Remark
Bottelneck: no issue
कार्य पूर्ण। पी0सी0आर0 प्रेषित। पंचवर्षीय अनुरक्षण के अन्तर्गत मार्ग का अनुरक्षण किया जा रहा है। -- as on 08-Apr-2024
Physical Peramenters