Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9.67 | 9.67 | 7.290 | 2.38 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
Span of Bridges [m] | 12 | 12 | 0.000 | 12 | 0.000 | 0.000 |
3W501 :
Administrative Approval Detail : 820/।।।(2)/20-7(प्रा0आ0)/2005 टी0सी0 दिनांक 13.05.2020
TS Amount (lakhs) : 570.9 Lacs
Financial Detail
Sanction Cost : 618.20 Lacs
Resanction Cost : 618.20 Lacs
Exp. Upto Last Fy : 461.99 Lacs
For CFY 2024-2025
Remaining : 156.21 Lacs
Demand : 39.75 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 9.75 Lacs
Total Up to Date Exp : 471.74 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
4 years 6 days ago
13 May 2020
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान एवं पार्ट-।। का कार्य पूर्ण। मार्ग में पड़ने वाले 12 मीटर स्पान सेतु का निर्माण कार्य प्रगति पर। अवशेष धनराशि रू 116.46 लाख की बचत है, जिसका समर्पण किया जाना है। -- as on 13-May-2024
Physical Peramenters