Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9.67 | 9.67 | 7.290 | 2.38 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
Span of Bridges [m] | 12 | 12 | 0.000 | 12 | 0.000 | 0.000 |
3W501 :
Administrative Approval Detail : 820/।।।(2)/20-7(प्रा0आ0)/2005 टी0सी0 दिनांक 13.05.2020
TS Amount (lakhs) : 570.9 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
618.20
Resanction Cost :
618.20
Tentative Cost :
484.06
Saving
134.14
Exp. Upto Last Fy : 461.99
For CFY 2024-2025
Remaining : 156.21
Demand : 39.75
Allotment : 50.00
Exp in CFY : 27.19
Total Up to Date Exp : 489.18
Construction Started
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 90 %
Sanction on :
4 years 2 months ago
13 May 2020
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग से सम्बन्धित कार्य पूर्ण कर लिये गये है। मार्ग के किमी0 7 में 12मी0 स्पान पुल का निर्माण कार्य प्रगति पर है। पुल एवं पुल का एप्रोच रोड एवं अन्य समस्त कार्य माह सितम्बर 2024 तक पूर्ण कर लिये जायेगें। -- as on 04-Jul-2024