Work Profile Report [3W569]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : 3606/III(2)/21-49(MLA)/2017
TS Amount (lakhs) : 6.28 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
18.00
Resanction Cost :
18.00
Tentative Cost :
18.00
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
18.00
Demand :
5.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Alignment Approved
Sanction on : 3 years 7 months ago
14 Sep 2021
Physical Progress:
At start of FY 2025-2026 :
10 %
Up to Date :
10 %
Tentative Completion date on : 10 months 2 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
समरेखण अनुमोदित। अग्रिम कार्यवाही की जा रही है। -- as on 10-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: