Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.55 | 4.55 | 0.000 | 4.55 | 4.550 | 0.000 |
3W702 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No 49618
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 276.09 Lacs
Resanction Cost : 276.09 Lacs
Exp. Upto Last Fy : 79.41 Lacs
For CFY 2024-2025
Remaining : 196.68 Lacs
Demand : 135.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.43 Lacs
Total Up to Date Exp : 79.84 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
10 months 2 hours ago
19 Jul 2023
Tentative Completion date:
2 months 1 week from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दिनांक 08.04.2024 को ठेकेदार के साथ र्हु इ बैठ क में ठेकेदार द्वारा दिये गये वर्क प्रोग्राम द्वारा 30.04.2024 तक इटर कोट का कार्य 31 मई 2024 तक टापकोट का कार्य एवं 30 जून 2024 तक पी.सी. का कार्य पूर्ण कर लिया जायेगा। रोड फनिचर इत्यादि का कार्य जुलाई 2024 तक पूर्ण कर लिया जायेगा। -- as on 23-Apr-2024
Physical Peramenters