Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.2 | 5.2 | 0.000 | 5.2 | 5.200 | 0.000 |
3W754 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No 64221/49
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
366.49
Resanction Cost :
366.49
Tentative Cost :
366.49
Exp. Upto Last Fy : 40.17
For CFY 2024-2025
Remaining : 326.32
Demand : 200.00
Allotment : 108.60
Exp in CFY : 35.26
Total Up to Date Exp : 75.43
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 40 %
Sanction on :
5 months 3 weeks ago
25 Jan 2024
Tentative Completion date:
6 months 1 week from now
25 Jan 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सोलिंग का कार्य पूर्ण, 4.00 किमी0 इण्टर कोट का कार्य पूर्ण एवं दीवारांे व स्कपर का कार्य 70 प्रतिशत पूर्ण। इन्टर कोट का कार्य 15 जुलाई 2024, टापकोट का कार्य अगस्त 2024, पी0सी0 का कार्य नवम्बर 2024 एवं रोड फर्नीचर का कार्य जनवरी 2025 तक पूर्ण कर लिया जायेगा। -- as on 01-Jul-2024
Physical Peramenters