Work Profile Report [3W819]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E File No 68356/2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
309.16
Resanction Cost :
309.16
Tentative Cost :
309.16
Exp. Upto Last Fy :
51.60
For CFY 2025-2026
Remaining :
257.56
Demand :
230.00
Allotment :
257.56
Exp in CFY :
170.47
Total Up to Date Exp :
222.08
Construction Started
Sanction on : 1 year 1 month ago
16 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
7 %
Up to Date :
55 %
Tentative Completion date on : 1 month 2 weeks from now
09 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वर्तमान में कार्य प्रगति पर है। -- as on 03-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: