Work Profile Report [3W819]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E File No 68356/2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
309.16
Resanction Cost :
309.16
Tentative Cost :
309.16
Exp. Upto Last Fy :
51.60
For CFY 2025-2026
Remaining :
257.56
Demand :
210.00
Allotment :
100.00
Exp in CFY :
98.66
Total Up to Date Exp :
150.26
Construction Started
Sanction on : 7 months 2 days ago
16 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
7 %
Up to Date :
20 %
Tentative Completion date on : 3 months 1 week from now
30 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सोलिंग एव 2.00 किमी. लम्बाई में इण्टर कोट का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 04-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: