Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 4.7 | 4.7 | 0 |
3W89 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. 1753/111(2)/05-63(प्रा.आ.)/05 दि. 14.10.05
TS Amount (lakhs) : 186 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
186.00
Resanction Cost :
186.00
Tentative Cost :
186.00
Exp. Upto Last Fy : 157.61
For CFY 2024-2025
Remaining : 28.39
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 157.61
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
18 years 9 months ago
14 Oct 2005
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। पी0सी0आर0 पे्रषित। -- as on 31-Jul-2020
Physical Peramenters