Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
40W10 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2847(1)।।।-2/05-79प्रा0आ0/05 दि0 19.12.05
TS Amount (lakhs) : 249.1 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
84.00
Resanction Cost :
249.10
Tentative Cost :
249.10
Exp. Upto Last Fy : 55.34
For CFY 2024-2025
Remaining : 193.76
Demand : 110.00
Allotment : 9.00
Exp in CFY : 8.84
Total Up to Date Exp : 64.18
Construction Started
Physical Progress:
At start of FY 2024-2025 : 6 %
Up to Date : 15 %
Sanction on :
18 years 6 months ago
19 Dec 2005
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 17: AIP Govt of India
Bottelneck: no issue
पूर्व स्वीकृत लागत के अन्तर्गत 1.50 किमी॰ लम्बाई पहाड कटान के सापेक्ष 0.28 कि॰मी॰ कार्य पूर्ण। अवशेष लम्बाई हेतु ई-फाईल सं॰ 51780/ 111262/2023 दिनंाक 29.03.2023 द्वारा पुनरीक्षित स्वीकृति प्राप्त। प्रथम बार कोई निविदा प्राप्त नहीं हुई। पुनः अधीक्षण अभियन्ता के पत्र सं0 2731/30याता0-7/2023, दिनांक 26-5-2023 द्वारा पुनः द्वितीय बार निविदा आमन्त्रित, कोई निविदा प्राप्त नहीं हुई। पुनः अधीक्षण अभियन्ता के पत्र सं0 3398/15याता0-7/2023, दिनांक 11-7-2023 द्वारा पुनः तीसरी बार निविदा आमन्त्रित की गई, जिसमें एक निविदा प्राप्त हुई। दिनांक 12-9-2023 को कार्य की फाईनेन्सियल बिड खोली गई। ठेकेदार की दरें अधिक होने के कारण दिनंाक 14-09-2023 द्वारा ठेकेदार को दरें कम करने हेतु पत्र लिखा गया जिसमें ठेकेदार द्वारा अपनी दरें दिनांक 22-09-2023 को दरे कम करने हेतु अपनी लिखित सहमति दी गई है। वर्तमान में कार्य प्रगति पर। -- as on 17-Feb-2024
Physical Peramenters