Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
40W102 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा॰सं॰ 5150/।।।(2)/10-18(प्रा॰आ॰)/2010 दिनांक 16-08-2010
TS Amount (lakhs) : 25.2 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
25.20
Resanction Cost :
25.20
Tentative Cost :
25.20
Exp. Upto Last Fy : 21.09
For CFY 2024-2025
Remaining : 4.11
Demand : 1.75
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 21.09
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
13 years 11 months ago
16 Aug 2010
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 11: AIP Division
Bottelneck: no issue
उत्तराखण्ड शासन के पत्र सं॰872/ एक्स-4-16/1(268) /2016 दिनांक 12.08.2016 सैद्वान्तिक स्वीकृति प्राप्त। इस कार्यालय के पत्र सं॰ 2948/13सी॰ दिनांक 12.10.2017 व पुनः पत्र सं॰ 2310/13सी॰ दिनांक 08.07.2021 द्वारा अनुपालन आख्या उप वन संरक्षक रुद्र्रप्रयाग को प्रेषित कर दी गई है। -- as on 22-Apr-2023
Physical Peramenters