Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 4.87 | 0.000 | 4.87 | 0.000 | 0.000 |
40W12 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 63(1)/।।।-2/06/91(प्रा॰आ॰)/05 दि0 16.01.06 एवं शा॰सं॰ 1679/।।।(2)/18-91 (प्रा॰आ॰)/2005 दिनांक 26-04-2018
TS Amount (lakhs) : 84 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
84.00
Resanction Cost :
223.34
Tentative Cost :
223.34
Exp. Upto Last Fy : 208.78
For CFY 2024-2025
Remaining : 14.56
Demand : 14.56
Allotment : 1.00
Exp in CFY : 0.02
Total Up to Date Exp : 208.80
Work completed
Physical Progress:
At start of FY 2024-2025 : 97 %
Up to Date : 97 %
Sanction on :
18 years 6 months ago
16 Jan 2006
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
कार्य पूर्ण। काश्तकारों को मुआवजा वितरण की कार्यवाही गतिमान है। उत्तराखण्ड शासन के पत्र सं॰ 537/X-4-17/1(840)/2015 दिनांक 05-12-2017 द्वारा विधिवत् स्वीकृति प्राप्त। -- as on 29-Apr-2024
Physical Peramenters