Work Profile Report [40W12]

चन्द्रापुरी से गुगली- आसों-जयकण्डी मोटर मार्ग का नव निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 63(1)/।।।-2/06/91(प्रा॰आ॰)/05 दि0 16.01.06 एवं शा॰सं॰ 1679/।।।(2)/18-91 (प्रा॰आ॰)/2005 दिनांक 26-04-2018

TS Amount (lakhs) : 84 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

84.00

Resanction Cost :

223.34

Tentative Cost :

223.34

Exp. Upto Last Fy :

208.78

For CFY 2024-2025

Remaining :

14.56

Demand :

0.02

Allotment :

1.00

Exp in CFY :

0.02

Total Up to Date Exp :

208.80

Work completed

Sanction on : 18 years 11 months ago

16 Jan 2006

Physical Progress:

At start of FY 2024-2025 :

97 %

Up to Date :

97 %

Tentative Completion date on : 2 years 8 months ago

31 Mar 2022

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
5
4.87
0.000
4.87
0.000
0.000

Remark

view all

कार्य पूर्ण। काश्तकारों को मुआवजा वितरण की कार्यवाही गतिमान है। उत्तराखण्ड शासन के पत्र सं॰ 537/X-4-17/1(840)/2015 दिनांक 05-12-2017 द्वारा विधिवत् स्वीकृति प्राप्त। -- as on 29-Apr-2024

Rating : 97

Forest Case Pending At : 21: Final

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand