Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
40W124 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा॰सं॰ 6700/।।।(2)/11-129(प्रा॰आ॰)/2011 दिनांक 22-12-2011
TS Amount (lakhs) : 50.4 Lacs
Financial Detail
Sanction Cost : 50.40 Lacs
Resanction Cost : 50.40 Lacs
Exp. Upto Last Fy : 7.34 Lacs
For CFY 2024-2025
Remaining : 43.06 Lacs
Demand : 6.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 7.34 Lacs
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
12 years 4 months ago
22 Dec 2011
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
भारत सरकार के पत्र संख्या 8बी॰/यू॰सी॰पी॰/06/71/2016/788 दिनांक 02-09-2022 द्वारा विधिवत् स्वीकृति प्राप्त। -- as on 22-Apr-2023
Physical Peramenters