Work Profile Report [40W17]

fत्रयुगीनारायण- तोषी मोटर मार्ग नव fनर्माण सेतु सfहत।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

  • alerts
  • Documents

    Samples

Administrative Approval Detail : 2555/।।।-2/06-41 (प्रा॰आ॰)/06 दि0 26.09.06

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

148.80

Resanction Cost :

451.79

Tentative Cost :

451.79

Exp. Upto Last Fy :

222.01

For CFY 2025-2026

Remaining :

229.78

Demand :

90.73

Allotment :

163.31

Exp in CFY :

118.94

Total Up to Date Exp :

340.95

Construction Started

Sanction on : 19 years 1 month ago

26 Sep 2006

Physical Progress:

At start of FY 2025-2026 :

50 %

Up to Date :

75 %

Tentative Completion date on : 3 days 10 hours ago

31 Oct 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
6
6
4.000
2
1.500
0.000
Bridge
1 (25m)
1 (25m)
0 (0.000m)
1 (25m)
0 (0.000m)
0 (0.000m)

Remark

view all

स्वीकृत लम्बाई 6.00 किमी0 व वास्तविक लम्बाई 5.50 कि॰मी॰ के सापेक्ष 5.00 कि॰मी॰ लम्बाई में पहाड कटान का कार्य पूर्ण। अवषेष लम्बाई में कार्य प्रगति पर। सेतु निर्माण हेतु संयुक्त सचिव, उत्तराखण्ड शासन, लो॰नि॰वि॰, अनुभाग-2, देहरादून की ई-पत्रावली सं॰ 58562/07 दिनांक 19-06-2025 द्वारा 30 मीटर स्पान स्टील गर्डर सेतु हेतु रु॰ 201.98 लाख की स्वीकृति प्राप्त।। -- as on 28-Oct-2025

Rating : 58

Forest Case Pending At : 01: Withdraw

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: