Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 0.000 | 6 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 25 | 25 | 0.000 | 25 | 0.000 | 0.000 |
40W17 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2555/।।।-2/06-41 (प्रा॰आ॰)/06 दि0 26.09.06
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 148.80 Lacs
Resanction Cost : 451.79 Lacs
Exp. Upto Last Fy : 154.42 Lacs
For CFY 2024-2025
Remaining : 297.37 Lacs
Demand : 150.00 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 15.58 Lacs
Total Up to Date Exp : 170.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 33 %
Up to Date : 33 %
Sanction on :
17 years 7 months ago
26 Sep 2006
Tentative Completion date:
1 year 1 month from now
30 Jun 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
भारत सरकार के पत्र सं॰8बी॰/ यू॰सी॰ पी॰ / 06/179/2020 /ए॰एफ॰सी॰/98 दि॰22-04-2021 द्वारा सैद्धान्तिक स्वीकृति प्राप्त। अपर प्रमुख वन सरंक्षक एवं नोडल अधिकारी, वन संरक्षण, इन्दिरानगर फाॅरेस्ट कालोनी, उत्तराखण्ड देहरादून के पत्रांक 1883/एम॰पी॰/यू॰के॰/ रोड़ /39084/2019दिनांक 02-02-2022 अपर प्रमुख वन सरंक्षक, भारत सरकार, पर्यावरण, वन एवं जलवायु परिवर्तन मंत्रालय, एकीकृत क्षेत्रीय कार्यालय, देहरादून को विधिवत स्वीकृति हेतु प्रेषित। स्वीकृति लम्बाई में 2.00 कि॰मी॰ लं॰ में पहाड कटान कार्य पूर्ण। कि॰मी॰ 3 में कार्य प्रगति पर। -- as on 14-Dec-2023
Physical Peramenters