Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.02 | 1.02 | 0.000 | 1.02 | 0.000 | 0.000 |
40W395 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. 2465(1)/।।।(2) /18-41 (प्रा0आ0)/2006 दिनांक 30.05.2018
TS Amount (lakhs) : 97.84 Lacs
Financial Detail
Sanction Cost : 97.84 Lacs
Resanction Cost : 97.84 Lacs
Exp. Upto Last Fy : 87.25 Lacs
For CFY 2024-2025
Remaining : 10.59 Lacs
Demand : 10.59 Lacs
Allotment : 5.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 87.25 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 96 %
Up to Date : 96 %
Sanction on :
5 years 11 months ago
30 May 2018
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 31-Jul-2020
Physical Peramenters