Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 0.000 | 3.5 | 0.000 | 0.000 |
40W493 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा॰सं॰ 51789.।/111834/2023 दिनांक 31-03-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
392.88
Resanction Cost :
392.88
Tentative Cost :
392.88
Exp. Upto Last Fy : 86.69
For CFY 2024-2025
Remaining : 306.19
Demand : 150.73
Allotment : 40.00
Exp in CFY : 39.63
Total Up to Date Exp : 126.32
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 40 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
9 months 2 weeks from now
03 May 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान, स्कैपर निर्माण का पूर्ण एवं दीवार निर्माण , Wbm G1 का कार्य प्रगति पर। -- as on 02-Jul-2024
Physical Peramenters