Administrative Approval Detail : e file 37789 dt 11-05-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
4.50
Resanction Cost :
4.50
Tentative Cost :
4.50
Exp. Upto Last Fy :
0.06
For CFY 2025-2026
Remaining :
4.44
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.06
Survey work done
Sanction on : 2 years 8 months ago
11 May 2023
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
5 %
Tentative Completion date on : 7 months 1 week from now
31 Aug 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
इस कार्यलय के पत्रांक संख्या 62/1सी दिनांक 09.01.2026 द्वारा संरेखण प्रस्ताव अधीक्षण अभियन्ता 8वा वृत लो नि वि नई टिहरी को प्रेषित। - -- as on 13-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: