Work Profile Report [43W1070]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : e file 50206 dt 05-11-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
194.27
Resanction Cost :
194.27
Tentative Cost :
194.27
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
194.17
Demand :
194.00
Allotment :
59.23
Exp in CFY :
59.23
Total Up to Date Exp :
59.33
Construction Started
Sanction on : 1 year 1 month ago
05 Nov 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
50 %
Tentative Completion date on : 3 months 4 weeks from now
15 Apr 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी3 का कार्य प्रगति पर है । -- as on 28-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: