Work Profile Report [43W1079]
Tenders
Project Activities
alerts
Administrative Approval Detail : e file 51381 dt 02-01-2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
171.68
Resanction Cost :
171.68
Tentative Cost :
171.68
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
171.58
Demand :
166.00
Allotment :
166.00
Exp in CFY :
42.52
Total Up to Date Exp :
42.62
Construction Started
Sanction on : 1 year 3 weeks ago
02 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
75 %
Tentative Completion date on : 3 months 16 hours from now
24 Apr 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
G1, G2 का कार्य पूर्ण। G3 का कार्य प्रगति पर है, G3 का कार्य 25.01.2026 तक पूर्ण कर लिया जायेगा। -- as on 20-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: