Work Profile Report [43W119]
Tenders
alerts
Samples
Administrative Approval Detail : शा0 764/111(2)/08-65/07/प्रा0आ0 दि0 24.3.08
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
140.00
Resanction Cost :
140.00
Tentative Cost :
140.00
Exp. Upto Last Fy :
31.60
For CFY 2025-2026
Remaining :
108.40
Demand :
20.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
31.60
Construction Started
Sanction on : 17 years 1 month ago
24 Mar 2008
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
20 %
Tentative Completion date on : 3 months 2 weeks from now
31 Aug 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
01 किमी० लम्बाई में पहाड़ कटान का कार्य पूर्ण, किमी0 02 मे ग्रामीणों द्वारा भूमि विवाद । -- as on 23-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: