Administrative Approval Detail : शा.सं. 1439/111 (2)/05/(प्रा0आ0)/05 टी0सी0 दि0 3.8.05

TS Amount (lakhs) : 111 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

111.00

Resanction Cost :

111.00

Tentative Cost :

111.00

Exp. Upto Last Fy :

109.01

For CFY 2024-2025

Remaining :

1.99

Demand :

1.50

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

109.01

Work deferred

Sanction on : 19 years 3 months ago

03 Aug 2005

Physical Progress:

At start of FY 2024-2025 :

78 %

Up to Date :

80 %

Tentative Completion date on : 7 months 3 weeks ago

31 Mar 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
8
8
6.250
1.75
0.000
0.000

Remark

view all

शासन के पत्र सं0 3352 दि0 21.7.22 द्वारा आपत्तियों में प्राप्त,आपत्ति का निराकरण कर मु0अ0 के पत्रांक 1542/08(242)याता-पौडी/23 दि0 08.06.23 द्वारा आगणन शासन को प्रेषित। -- as on 29-Oct-2024

Rating : 98

No Forest Case in The Work

No Hindrance / Bottleneck