Work Profile Report [43W216]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 5527/।।।(2)/10-04(एम0एल0ए0)/2010 दि0 13/12/2011
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
37.80
Resanction Cost :
37.80
Tentative Cost :
37.80
Exp. Upto Last Fy :
0.98
For CFY 2025-2026
Remaining :
36.82
Demand :
14.02
Allotment :
7.18
Exp in CFY :
7.18
Total Up to Date Exp :
8.16
Alignment Approved
Sanction on : 15 years 1 month ago
13 Dec 2010
Physical Progress:
At start of FY 2025-2026 :
25 %
Up to Date :
25 %
Tentative Completion date on : 1 year 10 months from now
30 Nov 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Proposal of land acquisition has been prepared, and landowners are being informed for the same. -- as on 01-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: