Work Profile Report [43W687]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 1914/111(2)/18-13(एम0एल0ए0)/ 2017 दि0 16.05.2018
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
92.10
Resanction Cost :
92.10
Tentative Cost :
92.10
Exp. Upto Last Fy :
49.33
For CFY 2025-2026
Remaining :
42.77
Demand :
1.50
Allotment :
1.34
Exp in CFY :
1.34
Total Up to Date Exp :
50.67
Phase1 DPR Submitted
Sanction on : 7 years 2 months ago
16 May 2018
Physical Progress:
At start of FY 2025-2026 :
15 %
Up to Date :
15 %
Tentative Completion date on : 2 months 1 week ago
31 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
ग्रामीणों द्वारा मार्ग की कुछ लम्बाई में भूमि देने से मना किया जा रहा है, जिस कारण कार्य बाधित है। -- as on 23-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: