Work Profile Report [43W698]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0 सं0 5077/111(2)/18-12(एमएलए)/2017 दि0 15.10.2018
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
74.53
Resanction Cost :
74.53
Tentative Cost :
74.53
Exp. Upto Last Fy :
2.13
For CFY 2025-2026
Remaining :
72.40
Demand :
12.87
Allotment :
13.18
Exp in CFY :
13.18
Total Up to Date Exp :
15.32
Phase1 DPR Submitted
Sanction on : 7 years 3 months ago
15 Oct 2018
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
5 %
Tentative Completion date on : 1 year 4 months from now
31 May 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
द्वितीय चरण स्टेज I का कार्य स्वीकृत, प्रतिकार वितरण कार्य प्रगति पर। -- as on 03-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: