Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 8 | 0 |
43W698 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 5077/111(2)/18-12(एमएलए)/2017 दि0 15.10.2018
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
74.53
Resanction Cost :
74.53
Tentative Cost :
74.53
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 74.53
Demand : 15.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
5 years 9 months ago
15 Oct 2018
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सर्वेक्षण कार्य पूर्ण, परन्तु ग्रामवासियों द्वारा सहमति प्राप्त नही हुयी है । पुनः सर्वेक्षण किये जाने पर भी ग्रामिणों द्वारा विवाद किया जा रहा है । -- as on 14-Jun-2021
Physical Peramenters