Work Profile Report [43W709]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 5065/111(2)/18-13/एम0एल0ए0/2017 टी0सी0 दि0 15.10.2018
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
41.64
Resanction Cost :
41.64
Tentative Cost :
41.64
Exp. Upto Last Fy :
12.04
For CFY 2024-2025
Remaining :
29.60
Demand :
0.50
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
12.04
Survey work done
Sanction on : 6 years 2 months ago
15 Oct 2018
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
10 %
Tentative Completion date on : 8 months 5 days from now
31 Aug 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पुनः सर्वेक्षण दिनांक 30/12/2024 तक कर लिया जायेगा। -- as on 22-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: