Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
43W893 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 2611/111(2)21-12/एमएलए/ 2017/टी0सी0-4 दि0 10.08.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
41.39
Resanction Cost :
41.39
Tentative Cost :
41.39
Exp. Upto Last Fy : 2.05
For CFY 2024-2025
Remaining : 39.34
Demand : 20.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.05
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 11 months ago
10 Aug 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मु0अ0 के पत्रांक 3305/08/194 याता-पौडी/2021 दि0 28.10.22 को आगणन आपत्ति में वापस। -- as on 15-Nov-2022
Physical Peramenters