Work Profile Report [43W895]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 5431/111(2)/21-13/ एम0एल0ए0/2017टी0सी0 111 दि0 12.11.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
77.54
Resanction Cost :
77.54
Tentative Cost :
77.54
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
77.54
Demand :
1.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Survey work done
Sanction on : 3 years 1 month ago
21 Nov 2021
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
10 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पुनः सर्वेक्षण कार्य पूर्ण। भू वैज्ञानिक आख्या अप्राप्त। -- as on 22-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand