Work Profile Report [43W901]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0 सं0 6175/111(2)/21-12(एमएलए)/2017 दि0 22.12.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
18.67
Resanction Cost :
18.67
Tentative Cost :
18.67
Exp. Upto Last Fy :
1.26
For CFY 2025-2026
Remaining :
17.41
Demand :
3.00
Allotment :
5.00
Exp in CFY :
2.98
Total Up to Date Exp :
4.23
Phase1 DPR Submitted
Sanction on : 3 years 1 month ago
21 Dec 2022
Physical Progress:
At start of FY 2025-2026 :
10 %
Up to Date :
10 %
Tentative Completion date on : 8 months 6 days from now
30 Sep 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
द्वितीय चरण स्टेज I का कार्य स्वीकृत। प्रतिकार वितरण कार्य प्रगति में। -- as on 03-Jan-2026