Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
43W903 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 2081(1)/111/2/21-13 /एम0एल0ए0/2017 टी0सी0 दि0 20.07.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
29.24
Resanction Cost :
29.24
Tentative Cost :
29.24
Exp. Upto Last Fy : 18.73
For CFY 2024-2025
Remaining : 10.51
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 18.73
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
3 years 11 months ago
21 Jul 2020
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रतिकर वितरण कार्य प्रगति पर है । -- as on 16-May-2024
Physical Peramenters