Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 2.500 | 0.5 | 0.500 | 0.500 |
43W934 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ाा0 सं0 2612/111(2)21-12/एमएलए/ 2017/टी0सी0 दि0 10.08.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
93.38
Resanction Cost :
93.38
Tentative Cost :
93.38
Exp. Upto Last Fy : 22.76
For CFY 2024-2025
Remaining : 70.62
Demand : 50.00
Allotment : 0.00
Exp in CFY : 17.98
Total Up to Date Exp : 40.74
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
10 Aug 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण।दायित्व शेष। -- as on 12-Jul-2024