Work Profile Report [43W977]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : 1703/111(2)20-13(एमएलए)/2017 टी0सी0 111 दि0 13.10.2020
TS Amount (lakhs) : 114.22 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
114.22
Resanction Cost :
114.22
Tentative Cost :
114.22
Exp. Upto Last Fy :
50.07
For CFY 2025-2026
Remaining :
64.15
Demand :
15.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
50.07
Work deferred
Sanction on : 4 years 9 months ago
13 Oct 2020
Physical Progress:
At start of FY 2025-2026 :
60 %
Up to Date :
60 %
Tentative Completion date on : 3 weeks 1 day from now
31 Aug 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अधिशासी अभियंता महोदय द्वारा ग्रामीणों के साथ दिनांक 24.05.2025 को बैठक की गयी लेकिन ग्रामीणों द्वारा सहमति नहीं दी जा रही है । -- as on 02-Aug-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: