Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 25 | 0 | 0 | 0 |
44W417 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 1730/।।।(2)/14-03 (मु0म0घो0)/2014 दिनंाक 14 सितम्बर, 2014
TS Amount (lakhs) : 132.73 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
243.54
Resanction Cost :
243.54
Tentative Cost :
243.54
Exp. Upto Last Fy : 171.31
For CFY 2024-2025
Remaining : 72.23
Demand : 72.23
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 171.31
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
9 years 10 months ago
14 Sep 2014
Tentative Completion date:
3 years 3 months ago
31 Mar 2021
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 09: GOI
Bottelneck: no issue
प्रभागीय वनाधिकारी नरेन्द्रनगर वन प्रभाग मुनिकीरेती के पत्रांक 3527/12-1 दिनंाक 11.06.2024 के द्वारा अपनी स्थल निरीक्षण आख्या नौडल अधिकार इन्द्रानगर फारेट कालोनी देहरादून को पे्रषित की गई है। -- as on 14-Jun-2024
Physical Peramenters