Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.47 | 0 | 2.000 | -2 | 0.470 | 0.000 |
44W599 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या-212/।।।(2)/21-11 (एम0एल0ए0)/2017 दिनंाक 11 फरवरी, 2021
TS Amount (lakhs) : 205.84 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
205.84
Resanction Cost :
205.84
Tentative Cost :
205.84
Exp. Upto Last Fy : 179.51
For CFY 2024-2025
Remaining : 26.33
Demand : 25.00
Allotment : 0.00
Exp in CFY : 4.17
Total Up to Date Exp : 183.69
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 80 %
Sanction on :
3 years 5 months ago
11 Feb 2021
Tentative Completion date:
1 month 1 week from now
31 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.00 कि0मी0 लम्बाई में पार्ट-।। का कार्य पूर्ण। शेष 0.47 लम्बाई में पार्ट-।। का कार्य प्रगति पर। -- as on 16-May-2024
Physical Peramenters