Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
44W621 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 501/।।।(2)/22-11 (एम0एल0ए0)/2017 टीसी-5 दिंनाक 07 जनवरी, 2022
TS Amount (lakhs) : 380.56 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
380.56
Resanction Cost :
380.56
Tentative Cost :
380.56
Exp. Upto Last Fy : 352.28
For CFY 2024-2025
Remaining : 28.28
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 352.28
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 6 months ago
07 Jan 2022
Tentative Completion date:
6 months 3 weeks ago
22 Dec 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 16-May-2024
Physical Peramenters