Administrative Approval Detail : ई पत्रावली संख्या-22183 लोक निर्माण अनुभाग-2 देहरादून दिनांक 07 अगस्त, 2023
TS Amount (lakhs) : 304.02 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
304.02
Resanction Cost :
304.02
Tentative Cost :
304.02
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
304.02
Demand :
151.05
Allotment :
106.06
Exp in CFY :
106.06
Total Up to Date Exp :
106.06
Construction Started
Sanction on : 1 year 4 months ago
07 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
40 %
Tentative Completion date on : 5 months 2 weeks from now
13 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0-1 का कार्य पूर्ण । जी0-2 का कार्य प्रगति पर है। -- as on 05-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: