Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 4.000 | 0.000 |
44W697 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या-22183 लोक निर्माण अनुभाग-2 देहरादून दिनांक 07 अगस्त, 2023
TS Amount (lakhs) : 304.02 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
304.02
Resanction Cost :
304.02
Tentative Cost :
304.02
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 304.02
Demand : 250.00
Allotment : 100.00
Exp in CFY : 0.62
Total Up to Date Exp : 0.62
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 10 %
Sanction on :
11 months 1 week ago
07 Aug 2023
Tentative Completion date:
10 months 3 weeks from now
13 Jun 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी0-1 का कार्य प्रगति पर है। -- as on 14-May-2024
Physical Peramenters