Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 4.000 | 0.000 |
44W697 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या-22183 लोक निर्माण अनुभाग-2 देहरादून दिनांक 07 अगस्त, 2023
TS Amount (lakhs) : 304.02 Lacs
Financial Detail
Sanction Cost : 304.02 Lacs
Resanction Cost : 304.02 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 304.02 Lacs
Demand : 250.00 Lacs
Allotment : 100.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 10 %
Sanction on :
9 months 1 week ago
07 Aug 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी0-1 का कार्य प्रगति पर है। -- as on 14-May-2024
Physical Peramenters