Work Profile Report [44W750]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : ई पत्रावली संख्या-71381/11 लोक निर्माण अनुभाग-2 देहरादून दिनांक 20 अगस्त, 2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1097.72
Resanction Cost :
1097.72
Tentative Cost :
1097.72
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
1,097.72
Demand :
300.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
in Tendering Stage
Sanction on : 4 months 1 week ago
20 Aug 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
0 %
Tentative Completion date on : 1 year 2 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
निविदा की फाईनेशियल बिड खेाली जा चुकी है। अनुबन्ध गठन का कार्य प्रगति पर। -- as on 27-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: