Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
No of Bridges | 2 | 2 | 0 | 2 | 0 | 0 |
Span of Bridges [m] | 18 | 18 | 0.000 | 18 | 0.000 | 0.000 |
45W132 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या-4417/।।।(2)15-04(मु0म0 घो0)/2015, दिनांक-27.05.2015।
TS Amount (lakhs) : 28.22 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
28.22
Resanction Cost :
28.22
Tentative Cost :
28.22
Exp. Upto Last Fy : 25.44
For CFY 2024-2025
Remaining : 2.78
Demand : 2.78
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 25.44
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
9 years 1 month ago
27 May 2015
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मोटर मार्ग पर द्वितीय चरण स्टेज-। के सापेक्ष 5.00 कि0मी0 लम्बाई पर पहाड़ कटान का कार्य पूर्ण। प्रथम चरण की स्वीकृति के सापेक्ष मुआवजा वितरण की कार्यवाही गतिमान। -- as on 23-Dec-2023
Physical Peramenters