Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 0.000 |
46W615 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन देहरादून का ई पत्रावली संख्या-30972 लोक निर्माण अनुभाग-2 देहरादून दिनांक 12 अक्टूबर 2023
TS Amount (lakhs) : 414.39 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
414.39
Resanction Cost :
414.39
Tentative Cost :
414.39
Exp. Upto Last Fy : 62.82
For CFY 2024-2025
Remaining : 351.57
Demand : 200.00
Allotment : 55.00
Exp in CFY : 52.94
Total Up to Date Exp : 115.76
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 40 %
Sanction on :
9 months 5 days ago
12 Oct 2023
Tentative Completion date:
9 months 4 weeks from now
15 May 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 21-Feb-2024
Physical Peramenters