Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.2 | 1.2 | 0.000 | 1.2 | 1.200 | 0.000 |
46W676 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन के ई पत्रावली संख्या- 33519/13 लोक निर्माण अनुभाग-2 देहरादून दिनांक 29 जनवरी, 2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
118.29
Resanction Cost :
118.29
Tentative Cost :
118.29
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 118.29
Demand : 118.29
Allotment : 71.00
Exp in CFY : 70.08
Total Up to Date Exp : 70.08
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 80 %
Sanction on :
5 months 2 weeks ago
29 Jan 2024
Tentative Completion date:
1 month 1 week from now
30 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 27-Mar-2024
Physical Peramenters