Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 3.000 | 0.000 |
46W682 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन के ई पत्रावली संख्या- 51399/13 लोक निर्माण अनुभाग-2 देहरादून दिनांक 05 मार्च 2024
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 119.83 Lacs
Resanction Cost : 119.83 Lacs
Exp. Upto Last Fy : 2.20 Lacs
For CFY 2024-2025
Remaining : 117.63 Lacs
Demand : 20.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.20 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 months 2 weeks ago
05 Mar 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 10-Apr-2024
Physical Peramenters