Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
47W123 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 6276/।।।(2)/10-07(एम0एल0ए0)/2010 दिनांक 13 दिसम्बर, 2010
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
50.40
Resanction Cost :
50.40
Tentative Cost :
50.40
Exp. Upto Last Fy : 1.63
For CFY 2024-2025
Remaining : 48.77
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.63
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
13 years 7 months ago
13 Dec 2010
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 15: AIP Nodal
Bottelneck: no issue
मार्ग के क्षतिपूर वृक्षारोपण के हस्तान्तरण नामान्तरण की कार्यवाही पूर्ण की जा चुकी है जिसमें जिलाधिकारी महोदय द्वारा हस्तान्तरण नामान्तरण के आदेश भी निर्गत किये जा चुके है। मार्ग की अनुपालन आख्या प्रभागीय वनाधिकारी नरेन्द्रनगर वन प्रभाग मुनिकीरेती को प्रेषित की जा चुकी है। मार्ग की क्षतिपूरक वृक्षारोपण एवं एन0पी0वी0 धनराशि परिवेश पोर्टल पर कुल रू0 1366121.25 के विरूद्ध रू0 1366121.00 प्रदर्शित कर रहा है। जिस कारण क्षतिपूरक वृक्षारोपण के हस्तान्तरण नामान्तरण की कार्यवाही नहीं हो पा रही है। उक्त धनराशि के संशोधन हेतु अपर प्रमुख वन संरक्षक नोड़ल अधिकारी देहरादून को आॅन लाईन पेमेन्ट ड़ीटेल भरकर प्रेषित कर दी गई है। -- as on 03-May-2024
Physical Peramenters