Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 0.000 | 7 | 0.000 | 0.000 |
47W129 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 1440/।।।ंं(2)/11-05(प्रा0आ0)/2010 दिनांक 28.03.2011
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
88.20
Resanction Cost :
88.20
Tentative Cost :
88.20
Exp. Upto Last Fy : 20.43
For CFY 2024-2025
Remaining : 67.77
Demand : 5.00
Allotment : 7.30
Exp in CFY : 7.23
Total Up to Date Exp : 27.66
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 5 %
Sanction on :
13 years 3 months ago
28 Mar 2011
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 11: AIP Division
Bottelneck: no issue
उक्त वन भूमि प्रस्ताव जिस आई0ड़ी0 से अपलोड़ किया गया है। वह किसी कारण नहीं खुल रही है जिस हेतु प्रभागीय वनाधिकारी नरेन्द्रनगर वन प्रभाग मुनिकीरेती को इस कार्यालय के पत्रांक-957/33सी0 दिनांक 01.06.2024 द्वारा पत्र लिखा गया है। 14 -- as on 14-Jul-2024
Physical Peramenters