Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 5.8 | 0.000 | 5.8 | 0.000 | 0.000 |
47W136 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 3376/।।।(2)/12-27 (सामान्य)/2010 दि0 05.10.2012
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
88.20
Resanction Cost :
88.20
Tentative Cost :
88.20
Exp. Upto Last Fy : 21.64
For CFY 2024-2025
Remaining : 66.56
Demand : 15.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 21.64
Survey work done
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
11 years 9 months ago
05 Oct 2012
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
मार्ग पर विधिवत स्वीकृति भारत सरकार के पत्रांक 8बी0/यू0सी0पी0/06/96/2017/एफ0सी0/934 दिनांक 06.10.2022 द्वारा प्राप्त। -- as on 09-Jul-2024
Physical Peramenters