Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 4.5 | 4.5 | 0 |
47W206 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0 सं0 1144/।।।(2)/14-72(प्रा0आ0)/2013 दि0 04.03.2014
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 62.24 Lacs
Resanction Cost : 62.24 Lacs
Exp. Upto Last Fy : 11.25 Lacs
For CFY 2024-2025
Remaining : 50.99 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 11.25 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
10 years 2 months ago
04 Mar 2014
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 11: AIP Division
Bottelneck: no issue
अपर प्रमुख वन संरक्षक एवं नोड़ल अधिकारी द्वारा म्यूटेशन आॅन लाईन सत्यापित किया जा चुका है। अनुपालन आख्या की कार्यवाही गतिमान है। -- as on 03-May-2024
Physical Peramenters